THE ICE STORM
The weather of the past two days played havoc with the ability of the electric company to complete the connection of permanent power to the building. We are hoping they are able to get back on track today. We can not complete the installation of the flooring in the school until the heat has been on for two days to allow the floor material for the Reception Room and the Hall to acclimate. This is required for proper installation.
In the meantime, the concrete flatwork contractor is moving ahead with the forming of the new sidewalks that are being placed in each courtyard. These are a requirement to allow equal access from classroom to playground for children of all physical abilities. Miss Sarah's courtyard is pictured below.